There is finally a light at the end of the tunnel! We spent almost a week over the Christmas break working on the house. Last year, the house was very uncomfortable to work in due to the heat. It couldn’t be more different this year. The house was lovely and cool, thanks to the thick stone blocks and fully insulated walls and ceilings. The bathrooms have most of their tiling done now:
The Exterior Walls – Preparation Work
I spent several hours pressure cleaning the outside stone block walls. I needed to clean off any loose crazed, flaky paint before I could repaint. In doing so, I made two discoveries. Number one – the house had at one stage been light green. And secondly – high pressure water very quickly eats into sandstone. Without its covering of paint, it was very easy to end up with holes in the stone.
After pressure cleaning, the walls looked a lot better. However, the now exposed stone would deteriorate if we didn’t repaint it.
The Exterior Walls – Painting!
I spent most of two solid days painting. I did two coats on parts of the exterior – the last of the cladding, touched up a few other places, the front stone wall and what I could reach of one side wall. The uneven surface of the stone blocks required quite a bit of pressure to ensure complete coverage with the paint and beyond a certain height, the roller became too long for me to exert the needed pressure. I also painted some of the trim in Basalt, architraves in the same and both sides of the back door. The interior of the door is white:
The front wall looks much better all in one colour:
But it looks even better with its dark Basalt trim:
I painted the last of the cladding as well:
The last wall I worked on was the other side wall but sun glare meant I could barely work out where I had painted. Instead, I did the windowsills and my husband painted the wall later.
Around the Back
On the first day, we took a crow bar to the remnant of the old concrete left along the back of the house.
We found there was more left than it looked. We broke it up (there was no reinforcing) and ended up taking 2 tonnes away to the concrete waste dump.
My husband and father-in-law framed up and concreted the area in sections while I painted. They have also left space for a drain along the edge. The entire backyard is concrete and we don’t want rain runoff to pool along the house. They sloped the newly laid concrete to run water away – the drain provides an extra back up in case of a large amount of rain in a short time.
Sharp eyes would have noticed a couple other differences in the above photo. I painted the exterior of the back door in Basalt, along with the architraves for the kitchen window.
A Little Before and After
We finally feel like there is an end to the must-be-done jobs! It is easy to forget how much has changed compared to what we have left to do. But in case you have, I have the before photo of just the front of the house:
And this photo I took earlier this week:
I will write a full before and after post once it is all done! I can’t wait to show you it finished!
Hasta luego and Happy New Year!